City’s closure of Flushing overpass causes businesses to suffer

THE COURIER/Photo by Eric Jankiewicz

The city’s extended closure of an overpass bridge in Flushing is set to end by 2016, according to a Department of Transportation (DOT) spokesman. But the long wait could continue to hurt local business owners.

LIRR train tracks cut through 149th Street, with an overpass bridge connecting the two sides of the street. The bridge has been closed since 2009, according to residents and business owners in the area.

According to a DOT spokesman, a new bridge was ready to open in 2012, but during a final inspection the department found cracks in the foundation, leading the department to keep the bridge closed.

The lack of a bridge in the area left several businesses on 41st Avenue disconnected from the other side. Traffic withered away as a result, business owners said, and led to a noticeable reduction in customers visiting the stores on 41st Avenue, near the 149th Street overpass bridge.

“I’m lucky if I get half the customers I used to get before the bridge closed,” said Kyung Yoon, who owns a deli on 41st Avenue. “It’s not good for business. We pay taxes, don’t we? So why are they taking so long to open it again?”

Yoon points out that there are other overpass bridges in the area but for most people they’re inconvenient to use.

The city’s spokesman said that the bridge will remain closed for public safety. He said they continue to meet with local stakeholders and they will continue to provide updates to the community as they work to “reopen this important connection.”

The spokesman pointed out that the city opened the bridge to foot traffic in response to the community’s needs.

While pedestrians can still use the bridge, the area has become a hang out spot for people who want to drink alcohol, residents said. And, for this reason, resident Karina Hernandez said she barely ever comes to the deli’s side of the tracks.

Karina Hernandez lives on the other side of the tracks and she often goes to Northern Boulevard instead because if she drives it’s too inconvenient to use one of the working overpass bridges. And if she walks, the people who hang out on the bridge deter her from making the journey.

“It’s so ridiculous that it’s been closed for this long,” she said. “I used to come to these places all the time. But now, I barely ever make it unless it’s during the day and I’m not driving.”

Along with Yoon’s deli, there is also a pharmacy-café, a Chinese restaurant and a Korean restaurant. The workers at the pharmacy-café and the Korean restaurant also noted that business hasn’t been as good over the last five years because of the closed overpass bridge.

The city plans on completing a final design in 2014. And in the fall of 2015 the spokesman expects a construction contract to be hashed out. The new overpass bridge should be completed within six months after that.